The New Technologies Demonstrator Programme is a scheme part of Defra's Waste Implementation Programme, New Technologies Workstream, to demonstrate advanced waste processing technologies in England. A pot of £30million was allocated to fund 10 demonstrator projects with the project being headed by Dave Brooks at Defra. The scheme is not on schedule for the ambitious targets that were initially set out by Defra, however 9 projects out of the initial 10 are now scheduled to be operational by April 2009, over 2 years behind projections.

The scheme

The scheme for the distribution of the £30million pot commenced in 2004 and was originally split into two rounds: [1][2]

  • ROUND 1: 5 demonstrator projects in operation by 31.12.05
  • ROUND 2: 5 demonstrator projects in operation by 31.12.06

There project had a huge response for the first round, with 71 pre-qualification questionnaire submissions being filed from interested parties. The quality of some of the bids were criticised by Martin Brockelhurst, Head of Waste Strategy, at the Environment Agency who remarked some of the applications were poor and came from a "young industry".[3]

Controversy

There have been concerns that the project is taking too long and some participants threatened to walk out.[4] On the 11th April 2006, Defra declared that its initial timescales were ambitious and projects were not on target.[5]

Of the 10 original projects planned a total of 9 have now been signed and includes gasification, in-vessel composting, anaerobic digestion and mechanical heat treatment. From the original target dates for operational demonstrator plants outlined in the initial assessment criteria only 2 projects are now operational (true as of 27.11.06).[6] On the 24 November 2006, Dave Brooks announced that the new target for all plants being operational by April 2009.[7]

The projects

Operational

  1. Greenfinch anaerobic digesters, Ludlow, Shropshire
  2. Bioganix in-vessel composting plant, Leominister

Contracts signed

  1. ADAS/Envar in-vessel composing plant, Shropshire
  2. Yorwaste gasification plant, Seamer Carr, Scarborough
  3. Premier Waste aerobic digestion plant, Durham
  4. Novera gasification plant, Dagenham
  5. Energos gasification plant, Isle of Wight
  6. Compact Power gasification plant, Avonmouth
  7. Fairport Engineering, mechanical heat treatment, Merseyside

Template:Waste management

References

  1. ^ New Technologies Demonstrator Programme: Assessment Criteria, www.defra.gov.uk, Accessed 27.12.06
  2. ^ Defra opens second round of £30m new technologies fund, www.letsrecycle.com, Accessed 27.11.06
  3. ^ Agency comments on bidders in Defra's new technologies fund, www.letsrecycle.com, Accessed 27.11.06
  4. ^ Bristol may walk away from New Technologies Programme, www.letsrecycle.com, Accessed 27.11.06
  5. ^ Four new technology waste plants achieve Defra approval, www.letsrecycle.com, Accessed 27.11.06
  6. ^ All Demonstrator Projects Now Signed, www.mrw.co.uk, Materials Recycling Week, Accessed 27.11.06
  7. ^ All Demonstrator Projects Now Signed, www.mrw.co.uk, Materials Recycling Week, Accessed 27.11.06