In project management, a terminal element is the lowest element (activity or deliverable) in a work breakdown structure(WBS); it is not further subdivided.

Terminal elements are the items that are estimated in terms of resource requirements, budget and duration, linked by dependencies and scheduled.

A terminal element is sometimes called a work package, although the two terms are not synonymous.