It will soon be reviewed to determine if there are any copyright issues. The content should not be mirrored or otherwise reused until the issue has been resolved. If substantial content is duplicated, unless evidence is provided to the contrary (e.g. evidence of permission to use this content under terms consistent with the Wikimedia Terms of Use or public domain status; see Wikipedia:Donating copyrighted materials), editors will assume that this text is a copyright violation, and will soon delete the copy.
Before removing this notice, you should:
|
Pieman River Power Development was a major hydroelectric development on the West Coast of Tasmania in the 1970s and 1980s.
Early History
See also Pieman River
Early traverses
Well-known photographers Olegas Truchanas and Peter Dombrovskis, together with John Hawkins and Howard Dean, canoed and photographed the Pieman in 1964.[1]
The damming of the river was the subject of a struggle between conservation groups and Hydro Tasmania, similar to Lake Pedder . The struggle went relatively unnoticed on mainland Australia - and it was the proposed Franklin Dam issue that was to catch a much wider Australian audience than the damming of the Pieman or King Rivers.
Approval
The Pieman River Power Development was approved by the Tasmanian government in 1971, construction began in 1974 and it was completed in 1987.[2]
Development
The development included three power stations and five dams:-
- Lake Murchison and Murchison Dam
- Lake Mackintosh, Tullabardine Dam and Mackintosh Dam (Mackintosh Power Station)[3]
- Lake Rosebery and Bastyan Dam (Bastyan Power Station) [4]
- Lake Pieman and Reece Dam (Reece Power Station) [5]
It also included work on the two major tributaries of the Pieman, the Mackintosh and the Murchison rivers.
Legacy
It remains Hydro Tasmania's most successfully multi-dammed catchment on the West Coast, and it was developed after the Upper Gordon Scheme (Lake Pedder) and was being completed in the era of the Franklin River controversy. It could be seen as the last major Power Development Scheme undertaken by the Hydro during its stage as an expanding dam-making enterprise. The King River and Henty River developments that followed required specifically challenging engineering on the part of Hydro, but were smaller projects in duration.
References
- ^ "Shooting the Franklin River". web.archive.org. Archived from the original on 21 February 2006. Retrieved 2 February 2007.
- ^ Scanlon, Andrew; Tasmania. Hydro-Electric Commission (1990), Water power, HEC, ISBN 978-0-7246-1683-1 page 24
- ^ Commissioned 1982
- ^ Commissioned 1983