Jump to content

Metra potential method

From Wikipedia, the free encyclopedia
This is an old revision of this page, as edited by Nameless23 (talk | contribs) at 12:58, 6 December 2014 (formatting). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

The metra potential method (MPM) (Méthode des potentiels Métra) was developed by French researcher Bernard Roy in 1958 for the construction of the French paquebot France and of the first French nuclear power plant.

MPM is a means of describing organizing and planning a project. It is an equivalent of the PERT method.

Using summits for tasks and path for interdependencies between the different tasks, the solution is set are graphically.

Using MPM, the length of the critical path is shown directly in the diagram and the critical path itself can be identified easily.

References