As the name implies, Microtunneling is often used to construct small tunnels. These small diameter tunnels make it impossible to have an operator in the machine itself. Instead the machine must be operated remotely. Usually the operator controls the machine from a control room on the surface of the ground. The operator is given constant feedback about the machine’s location, orientation and hydraulic devices via a computer console. Most machines also have video cameras set up to give the operator more information. The operator can then control the MTBM and the jacking frame from the safety of the control room.

In most microtunning operations the pipe is inserted from the entry and pushed behind the machine. This is a process often called “Pipe Jacking”. As the machine advances, more tunnel liner is pushed from the entrance. Thus the speed of the advancing machine is controlled by the speed the pipe is inserted into the entrance.

As the length of tunnel increases the friction of the ground around the pipe increases as well. Usually two practices are used to minimize this friction. First, over-cutting is used to give a slight gap between the inner edge of the tunnel and the outer edge of the liner. Usually this is achieved by use of a cutter wheel that has a diameter ½ to 4 inches larger than the outside edge of the liner. Second, an economical and ecologically friendly lubricant(often betonite slurry) is injected into this gap. In addition to lubrication, this liner prevents the gap from collapsing.

While the friction can be reduced, it can never be eliminated, and so hundreds of tons of force are required to push the machine and liner into the ground. A large “jacking frame” is required to produce these forces. In most cases the entrance must be modified to support this frame and the forces it generates.

In addition to the jacking frame, smaller jacks, called “interjacks”, may be inserted between sections of tunnel liner. These push the two sections of liner apart. Friction on the liner sections between the Interjack and the entrance helps to prevent the liner from sliding out backwards. So while the liner behind the Interjack does not move, those sections in front of it receive additional pushing force.


Additional information can be found at