Linear scheduling method

From Wikipedia, the free encyclopedia
This is an old revision of this page, as edited by Erik9bot (talk | contribs) at 20:03, 30 May 2009 (add template:uncategorized). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Linear Scheduling Method (LSM) is a graphical scheduling method focusing on continuous resource utilization in repetitive activities. It is believed that it originally adopted the idea of Line-Of-Balance method.

LSM is used mainly in construction industry to schedule resources in repetitive activities commonly found in highway, pipeline, high-rise building projects. These projects are called repetitive projects or linear projects. The main advantages of LSM over Critical Path Method (CPM) is its underlying idea of keeping resource work continuously. In other words, it schedules activities in such a way that:

  1. resource utilization is maximized.
  2. interruption in on-going process is minimized, including hiring-and-firing.
  3. effect of learning curve phenomenon is minimized.

These benefits are achieved in LSM by schedule activity start date at the date which will provide such a continuous work flow for the resource. In contrast to CPM, this date scheduled by LSM is not the earliest possible start date of an activity. ...?

Graphical presentation of LSM is also another advantage over Critical Path Method when project consists of repetitive activities.

See also

Further reading

Linear (or Repetitive,or Time-Location based) Scheduling Software