131.110.83.17 16:42, 4 January 2007 (UTC)The statement critical path has no float is not correct. Critical path is defined as "the longest path through the network with the least amount of float. The critical path can contain float. But, it contains the least amount of float.
I disagree
A better
The critical path will be the path with the least amount of float, but many experts believe the critical path of a schedule should have no float. While it is possible for a critical path to have float, such float is most likely the result of a project completion constraint (i.e., a "Must Finish" constraint) in the scheduling software, which will give a project that is ahead of schedule postitive float and a project that is behind schedule negative float. —The preceding unsigned comment was added by Pkurtross (talk • contribs) 19:28, 14 May 2007 (UTC).