Dies ist eine alte Version dieser Seite, zuletzt bearbeitet am 7. Januar 2023 um 15:49 Uhr durch 10mmsocket (Diskussion | Beiträge) (Reverted 1 edit by Barny22 (talk): Sorry, but the reference updated doesn't say anything about actual voltages. Need to point to a better reference to support the article change). Sie kann sich erheblich von der aktuellen Version unterscheiden.

Vorlage:Short description Vorlage:Infobox power transmission line

NeuConnect is an HVDC submarine power cable under construction between England and Germany. [1] [2] [3] [4]

Project Status

As of December 2022, early construction works have started in Wilhelmhaven and Isle of Grain,[4] and manufacture of the cable has started.[5] The main construction phase will start in 2023.[4]

As of October 2022, operation is expected to start in 2028.[5]

Route

The cable will run between a new substation[6] on the Isle of Grain, in Kent in England to the new Fedderwarden substation in Wilhelmshaven in the Lower Saxony region of Germany.[2][3] Landfall will be next to Grain Coastal Park, in Kent, and at Hooksiel, near Wilhemshaven in Germany.[6]

At 725km in length, the interconnector will be one of the longest in the world.[7]

Specification

The HVDC link will consist of two main cables, each approximately Vorlage:Convert long, together with a much thinner fibre optic cable for temperature and acoustic sensing for about Vorlage:Convert from each landfall. The DC element will operate at 500Vorlage:NbspkV,[2] with a maximum capacity of 1,400Vorlage:NbspMW.[6]

Economics

The project is privately financed and will cost £2.4Bn (€2.8Bn). The project will deliver £1.7Bn in consumer benefits to UK consumers over 25 years, and could deliver a net reduction in carbon emissions of over 13MtCO2 in the same time.[7]

History

Neuconnect Britain Ltd. was established in 2018.[7]

NeuConnect received Interim Project Approval from Ofgem in January 2018.[8]

Public consultation events were held in July 2019.[8]

In December 2019, the planning application was submitted to Medway District Council.[8]

In December 2019, Invitations to Tender were launched for the procurement of two converter stations and 720Vorlage:Nbspkm of HVDC cabling.[8]

In December 2019, the Invitation to Tender (ITT) stage was launched to procure two converter stations and 720Vorlage:Nbspkm of HVDC cables.[9]

In January 2020, the Federal Network Agency in Germany (BNetzA) confirmed the NeuConnect interconnector project in its 2019-2030 grid development plan.[8]

In April 2020, Neuconnect completed site survey work on the Isle of Grain.[10]

A €1.2 billion cable contract was awarded in February 2022,[11] [12] and substations contract in April. [13] [12]

In July 2022, the project reached financial close, allowing early construction works to begin later in 2022. [7]

In October 2022, the cable manufacturer Prysmian started production of the 725km cable.[5]


See also

References

Vorlage:Reflist

  1. Project Overview. NeuConnect, abgerufen am 25. Januar 2020.
  2. a b c NeuConnect Interconnector. In: 4Coffshore. Abgerufen am 25. Januar 2020.
  3. a b Project 309 - NeuConnect. In: TYNDP 2018 Europe's Network Development Plan to 2025, 2030 and 2040. entsoe, abgerufen am 25. Januar 2020.
  4. a b c NEUCONNECT COMPLETES A YEAR OF SIGNIFICANT MILESTONES WITH EARLY WORKS NOW UNDERWAY ON FIRST EVER UK-GERMAN ENERGY LINK. In: NeuConnect News. NeuConnect, abgerufen am 23. Dezember 2022.
  5. a b c CABLING PRODUCTION STARTS ON NEUCONNECT IN IMPORTANT MILESTONE FOR FIRST EVER UK-GERMAN ENERGY LINK. In: NeuConnect News Releases. NeuConnect, 4. Oktober 2022, abgerufen am 5. November 2022.
  6. a b c Proposals for the NeuConnect Interconnector Public Information Leaflet. NeuConnect (neuconnect.eu [PDF; abgerufen am 26. Januar 2020]).
  7. a b c d FIRST EVER UK-GERMAN ENERGY LINK MOVES AHEAD AS £2.4BN/€2.8BN NEUCONNECT PROJECT REACHES FINANCIAL CLOSE. (Press release) In: NeuConnect News. 7. Juli 2022, abgerufen am 9. September 2022.
  8. a b c d e Project News. NeuConnect, abgerufen am 25. Januar 2020.
  9. NEUCONNECT’S MAJOR £1BN PROCUREMENT PROGRAMME MOVES TO NEXT STAGE, KEEPING VITAL NEW ENERGY LINK FIRMLY ON TRACK. Abgerufen am 26. April 2020.
  10. NEUCONNECT COMPLETES SITE SURVEY WORKS AS NEW ENERGY LINK CONTINUES TO MAKE GOOD PROGRESS. In: NeuConnect. Abgerufen am 26. April 2020.
  11. Prysmian Wins EUR 1.2 Billion Contract to Deliver UK-Germany Interconnector. In: Offshore Wind. 2. März 2022;.
  12. a b NEUCONNECT AWARDS OVER £1.5BN OF MAJOR CONTRACTS AS FIRST EVER UK-GERMAN ENERGY LINK MOVES AN IMPORTANT STEP CLOSER. In: News. NeuConnect, 11. April 2022, abgerufen am 22. April 2022: „Contractors selected for cabling and converter station works on new interconnector that will connect two of Europe’s largest energy markets for first time“
  13. Siemens Energy receives order for power connection to Great Britain. In: www.windtech-international.com.